Water

Three Boreholes, Three Timelines, One Budget Line

By Kelechi Umeadi · 02 Aug 2026 · 5 min read
Water treatment infrastructure under construction

A single budget line can cover several physical sites at once, and that is where public tracking often gets confusing. A rural water scheme announced for three communities is, on paper, one project with one published figure. On the ground, it is three separate boreholes, three separate contractors' visits, and — as we found — three quite different rates of progress.

We began following this scheme after residents in one of the three communities asked whether their site had been dropped from the plan. The published contract made no distinction between the three locations, so the only way to answer the question honestly was to visit each site and record what was actually there.

What each site visit showed

The first site, closest to the main access road, had a completed borehole and an operating hand pump within the stated window. The second, roughly nine kilometres further along an unpaved track, had drilling equipment on site but no completed structure. The third had no visible activity at all — no equipment, no markers, nothing beyond a faded signboard naming the project.

None of this was obvious from the original announcement, which listed a single completion date covering all three communities. Our site visit notes recorded the condition of each location separately, with dates, so residents in the third community had something concrete to raise with their ward representative rather than a general sense of neglect.

  • Site one: borehole completed and in use as of the visit date
  • Site two: drilling underway, no completed structure
  • Site three: no observable work at the published location

Why we separate the sites in the record

Grouping three distinct sites under one figure makes the overall project look further along than any single community is actually experiencing. Splitting the record by site, with its own dated note, gives a more honest picture — and it also gives the implementing agency a specific, answerable question rather than a broad complaint they can deflect. We shared our findings with the relevant water board and included their reply in the published record once it arrived.